Ed Sylvis Construction Logo Click Here to Return Job Site Photographs Index Page

Correcting a Sagging Floor

1
Click to Enlarge
The homeowner said the dwelling was less than four years old with a greater than a five inch sag in the floor of their 38' x 50' living room. Several contractors had suggested the only means of repair would be to move out every piece of furniture, brace the walls, remove and replace the floor system that was Mexican tile over 1-1/8" plywood sub floor.
2
Click to Enlarge
The only crawl access was more than 100 feet away from the sagging floor section. There was no cross ventilation. When I reached this area the air was damp and heavy. Fungus was growing on the rotted glu-lam girders and floor joists. Pier posts had rotted in their metal brackets.
3
Click to Enlarge
Plywood shear panels easily crumbled with a soft spank with the palm of my hand.
4
Click to Enlarge
We cut the tiled decking outside the living room, excavated an access ramp, and cut a window in the foundation. Damp air, under compression billowed out of the window for some time.
5
Click to Enlarge
Additional pier footings were excavated to allow the introduction of smaller support beams.
6
Click to Enlarge
Breaking new windows through the foundation stem into the new air shaft.
7
Click to Enlarge
Two men were required to operate these heavy 90lb jack hammers in a confined 18" space.
8
Click to Enlarge
Smaller 30lb hammers were used to trim the window to size.
9
Click to Enlarge
New treated floor joists were introduced adjacent to the rotted members.
10
Click to Enlarge
New joists were shimmed and blocked then tied to new girders with wood screws and framing anchors.
11
Click to Enlarge
A self leveling transit was used to monitor progress in the lifting process.
12
Click to Enlarge
The new girders and joists were lifted methodically to re-establish the floor plane.
13
Click to Enlarge
The final remnants of the rotted glu-lam joists and girders were hauled to the city dump.
14
Click to Enlarge
The appreciative homeowner gratefully writes a final project check for the successful restoration of the floor system to its original plane. All of this without moving any furniture or cracking any of the Mexican floor tiles.

 

[_private/navbar.htm]